Zijin Mining to start after the accident assessment deadline for dealing with the existing sewage
BEIJING, July 23 Xinhua Fuzhou (Zhang Yu) from Longyan City's 23, was informed that at present, Purple Mountain gold and copper wet plant has been fully suspend production for rectification, and environmental protection department for the deadline for dealing with the existing Zijin Mining sewage. Meanwhile, post-accident assessment of work in full swing. P>
learned, Longyan municipal government recently has set up a follow-up emergency response Zijin Mining Accident Command, stationed in Purple Mountain area, by the Deputy Mayor Lin Xinglu as commander, proper disposal of environmental safety Zijinshan gold and copper mine problem. P>
relevant departments will Zijinshan gold and copper solutions of various yard and pool the existing process water and wastewater seepage control measures and pollution control measures in a comprehensive investigation, and properly dispose of the existing water and wastewater technology ; of the Purple Mountain gold and copper mining area of the process the whole system, preventing system, anti-flood system, mine production system, environmental protection, security systems, and tailings, etc., to conduct a comprehensive investigation hidden danger. In troubleshooting, and corrective measures have not been approved provincial environmental protection and other relevant departments before the company can not resume production p>
At the same time, post-accident assessment of work in full swing. Departments will result in the seepage system accidents, environmental impact, mining geology, to carry out post-evaluation work; Dingjiang River Teshu combination of geology, climate and ecological environment, the environmental safety of relevant, flood control drainage, production layout, etc. conduct a comprehensive assessment and develop appropriate rectification plans in place to ensure that prevention, not to mine production and its surrounding environment pollution Dingjiang. P>
In addition, the Purple Mountain mine has organized stringent flood flood contingency plans against possible impact of severe weather, to ensure the safety of the flood season typhoon season. According to Purple Mountain gold and copper plant infrastructure wet forest sword Department briefing, he only had a day where the group of 6 sets of hook machine, more than 60 working day and night fighting, the construction of flood discharge trench around the plant to prepare for storm water discharge in flood season. (END) p>